Permit Submission Requirements
|
Quick Links: |
- Application Form
- Demolition Declaration Form
- Commitment to General Review by a professional engineer where required
- Site/grading plan prepared by a professional engineer (P.Eng.), or an Ontario land surveyor (OLS)
- All applicable necessary approvals
- Application Form
- Site Evaluation Report/ test pit information
- A site plan drawing showing the following:
-
- Property lines
- Location of the proposed on-site sewage system
- Location of all existing and proposed buildings and structures on the property
- Location of all wells on the property
- Location of any wells located within 30m of the proposed on-site sewage system
- Location of all existing and proposed driveways, laneways or similar on the property
- Location of all swales on the property
- Location of all bodies of water within 15m of the proposed on-site sewage system
- Location of all reservoirs within 15m of the proposed on-site sewage system
- Location of all easements on the property
- Location of all existing on-site sewage systems on the property
- Setback dimensions from the proposed treatment units, distribution piping and leaching chambers to each of the items listed in c through k above.
-
- Sewage system design and construction drawings including;
-
- Plan view
- Cross section (longitudinal and bilateral to the bed)
-
- The completed Addendum to Application to Permit Sewage System Construction or Repair Form
- Application Form
- Site plan
- Floor plan, foundation and framing plan
- Elevation(s)
- Section or detail of guard
- Detail Section (through deck view)
- Application Form
- Site Plan or survey
- Foundation plan
- Floor Plan (framing)
- Building Elevations
- Detail or Building Section
- Application Form
- Site Plan
- Grading and Drainage Plan prepared by a professional engineer (P.Eng.), if applicable
- Foundation plan
- Floor Plan(s) (one per floor, including framing elements, all dimensions, room names or uses, and any new plumbing facilities)
- Building Elevations
- Building and Detail Section
- Letter of verification from heating designer of the sufficiency of capacity of the existing heating
- Additional information on Existing System Sewage System may be required (where applicable)
- Completed EEDS form (OBC Part 12, SB 12)
- Application Form
- location plan or Site Plan where required
- Approved Site Development Plan and Agreement (for townhouses, multi’s and apartments)
- Any of the following construction plans as applicable
- Foundation plan
- Floor Plan(s) (one per floor, including framing elements, all dimensions, room names or uses, and any new plumbing facilities)
- Building Elevations
- Building and Detail Section
- Letter of verification from heating designer of the sufficiency of capacity of the existing heating
- Additional information on Existing System Sewage System may be required (where applicable)
- Where renovation is extensive a completed EEDS form may be required (OBC Part 12, SB 12)
- Application Form
- Site Plan, Grading and Drainage Plan prepared by a professional engineer (P.Eng.), or Ontario land surveyor (OLS)
- Completed EEDS form
- TARION (ONHWP) Registration Form
- Verification of potable water supply if applicable
- Foundation Plan
- Floor Plan (one per floor, including all structural framing elements, dimensions, room names and proposed plumbing fixtures)
- Engineered Floor and Roof Framing Plans (include engineered floor and roof truss drawings)
- Building Elevations (4 sides)
- Building and Detail Section
- Mechanical Ventilation Design Summary Form
- Heat Loss / Heat Gain Calculations and Furnace make/model
- “New Building Service Report” from the County of Oxford Water and Wastewater Service Department (if municipally serviced)
- Energy Efficiency Design Summary form
- Information sheet for MDS I calculation (if applicable)
- Copy of deed or Record of Transfer may be required for newly created lots in Registered Plans (if applicable)
- Application Form
- Approved Site Development Plan and Agreement (see Township Site Plan Control by-law)
- Geotechnical Investigation Report
- Site Plan, Grading and Site Servicing Plan (s) prepared by a professional engineer (P.Eng.), and an Ontario land surveyor (OLS) (see Subsection 4.2 and 4.3 of the by-law)
- Commitment to General Review by a professional engineer and Architect where Division C, 1.2 applies
- Verification of on-site water supply for firefighting
- Architectural Drawings (sealed)
- Structural Drawings (sealed)
- Mechanical Drawings (sealed)
- Electrical Drawings (sealed)
- Sprinkler and Standpipe Drawings (sealed) where applicable
- Energy efficiency design compliance summary form (OBC Part 12; SB 10)
- Copy of deed or Record of Transfer may be required for newly created lots in Registered Plans (if applicable)
- Application Form
- Approved Site Development Plan and Agreement (see Township Site Plan Control by-law)
- Geotechnical Investigation Report
- Site Plan, Grading and Site Servicing Plan (s) prepared by a professional engineer (P.Eng) and an Ontario land surveyor (OLS) (see Subsection 4.2 and 4.3 of the by-law)
- Commitment to General Review by a professional engineer and/or Architect, where Division C, 1.2 applies
- Verification of on-site water supply for firefighting
- Where applicable, a complete Private Sewage System Permit Application (see 2., above)
- Architectural Drawings (sealed)
- Structural Drawings (sealed)
- Mechanical Drawings (sealed)
- Electrical Drawings (sealed)
- Sprinkler and Standpipe Drawings where applicable (sealed)
- Application Form
- Site Plan (confirmation of location of building by OLS for MDS II purpose may be required)
- Commitment to General Review by professional engineers, where OBC Division C, Section 1.2 applies
- Site Characterization Report and Commitment to General Review (where required by the Nutrient Management Regulations)
- Foundation Plan (sealed)
- Floor Plan including interior penning and room layouts and uses (sealed)
- Structural Plans and Specifications (sealed)
- Building Section (sealed)
- Engineered Roof Framing Plans
- Confirmation of Drain relocate/disconnection (by Municipal Drainage Superintendent, where applicable)
- Application Form
- Site Plan
- Geotechnical review where new foundation system or ballasting is required
- Structural Drawings or specifications
- Elevations where applicable
- Sections and Detail where applicable
- MDS II calculations if applicable (nutrient storage facilities)